The goal
Give both teams one intake process, clear request ownership, and an agreed route for escalations.
Independent demonstration / Project delivery
A fictional five-week rollout of a shared service-request process for two internal support teams.
Independent portfolio demonstration using fictional data. This is not a Vizient or client deliverable.
I start by defining the boundaries of the work, then give each milestone an owner and a clear completion point.
Give both teams one intake process, clear request ownership, and an agreed route for escalations.
Includes process design, a pilot, training, and handover. Replacing the existing software is outside scope.
| Milestone | Owner | Target | Ready when |
|---|---|---|---|
| Agree scope and ownership | Project manager | Week 1 | Both team leads approve the process boundaries. |
| Design and test the workflow | Operations lead | Weeks 2–3 | Pilot feedback is reviewed and priority fixes assigned. |
| Confirm training coverage | Sponsor | Week 4, day 2 | Training times and support coverage are approved. |
| Prepare the teams | Team leads | Week 4 | Staff receive guidance and remaining pilot actions close. |
| Roll out and hand over | Operations lead | Week 5 | Readiness is confirmed and an operational owner accepts handover. |
Training depends on the sponsor’s coverage decision. If that decision slips past week 4, day 2, I would review the rollout date with the team before promising it.
A plan is useful when it makes the next action clear. I would review ownership and dependencies regularly, rather than treat the timeline as fixed.