Overall status
Needs attention
The pilot review is complete. Week 5 remains the planned rollout, but training coverage needs approval.
Independent demonstration / Operational visibility
A fictional status report at the end of week 3 of the same service-request rollout.
Independent portfolio demonstration using fictional data. This is not a Vizient or client deliverable.
I separate what has happened from what needs a decision, so a reader can understand the situation without sitting through every project meeting.
Overall status
The pilot review is complete. Week 5 remains the planned rollout, but training coverage needs approval.
Decision needed
Sponsor decision due week 4, day 2. Proposed approach: two smaller sessions to maintain support coverage.
| Workstream | Current position | Next action | Owner |
|---|---|---|---|
| Process design | Scope and ownership agreed | Keep the approved process available to both teams | Project manager |
| Pilot | Review complete | Close the remaining priority actions | Operations lead |
| Training | Coverage decision outstanding | Approve the two-session approach | Sponsor |
| Handover | Planned for week 5 | Confirm readiness after training | Team leads |
Risk: limited staff availability could delay training. Response: reserve backup sessions. Trigger: if coverage is unresolved by the decision deadline, review the rollout date.
I would close the update with a specific request: “Please confirm the training approach by week 4, day 2, so team leads can finalize attendance.”